Paralysis
by Analysis
The latest Videos, including NRC Chairman Jerkszo. It is clear to me, that he is in Way Over His Head (Double Entendre Intended). http://www.omaha.com/article/20110628/NEWS01/706289909#nrc-nuke-disaster-risk-low
Notice how when faced with a condition outside the box (accepted analyses and assumptions), the NRC is completely inept.
Get the DAMN Barges in NOW stupid! These guys will
mull it over and watch it burn. Paralysis by Analysis.
- - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - -
My co-workers are concerned. We talked this morning.
One of them has an inside track to the NRC "ears." I already provided
the following recommendations:
- Barges with Pumps and Generators (Assessment on Moorings
breaking free is correct - I was a licensed Merchant Marine Engineer when I was
a kid - but I can't think of anything else right now - I'm open to
suggestions).
- Ensure Back Up Nitrogen Supply to the Refueling Pool Cavity Seal because if it fails, then the Water above the Reactor Vessel (it is open for Refueling), will dump
- Re-Fill the RWST (Refueling Water Storage Tank) - In this configuration, the Reactor AND Spent Fuel Pool may be Gravity Fed to a point with this tank FULL
- Re-fill the SITs (Safety Injection Tanks) - and
Recharge their Nitrogen Charge - These are 2500 Cubic Foot Volumes of Borated
Water, charged to 200PSIG with a Bladder. There are 4 of them. With just
Nitrogen Pressure, you can inject borated water into the Reactor AND IF the
Fuel Transfer Tube Valve is OPEN, you can inject into the Spent Fuel Pool too.
- The Battery Rooms at Calhoun are on the 1011 Foot
Level - See Attached FIG 8.4-3 "Auxiliary Building Battery Rooms" of
the Attachment. DC Cables run
everywhere though. I confirmed that Massive Flooding External Events were NOT
analyzed for (because they were incredible).
He agreed and IS making those recommendations to the
NRC staff now.
I mentioned that other industrial Facilities are
vulnerable also and may result in power shortages which could remove OFF-Site
Power to Fort Calhoun. Also, if a Dam burst occurs, Intake Structure
(that separate building on what USED to be the River Front) would have
difficulty taking suction due to an effect known as "Vortexing."
As far as someone offering to buy up all the land
around Fort Calhoun, I don't know. Contamination may occur in high water IF
the Radwaste Storage Tanks, Chemical Volume and Control Boric Acid Storage
Tanks, Miscellaneous Waste Tanks, Spent Resin Metering Tanks, and
Demineralizers back up and via Floor Drains and flow out the Tank Vents. (oh, I
forgot the Steam Generator Blowdown Tanks to name a few sources but there are
more).
So much to think about and I have Day Job, but I
will always find time to answer your correspondence. I goofed off this weekend
and went to a Ham Field Day here. Was good to think about something normal.
Respectfully always,

- - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - -
I mentioned this concern about portable equipment.
It happened. See event report. These are the last ditch generators and fuel oil
supply WHEN they lose their onsite electrical distribution systems. The
Installed Diesels will be useless when they lose their Distribution Systems. The
Portable Generators are now useless. Off-site Power is
"iffy." Flooding is occurring
on lower elevations of plant.
I recommend Barges with Pumps and Generators aboard
anchored off the plant.
|
Power Reactor |
Event Number: 46989 |
|
Facility: FORT CALHOUN |
Region: 4 State: NE |
|
Unit: [1] [ ] [ ] |
RX Type: (1) CE |
|
NRC Notified By: NATHAN SEID |
HQ OPS Officer: DONALD NORWOOD |
|
Notification Date: 06/26/2011 |
Notification Time: 12:22 [ET] |
|
Event Date: 06/26/2011 |
Event Time: 10:45 [CDT] |
|
Last Update Date: 06/26/2011 |
|
|
Emergency Class: NON EMERGENCY |
|
10 CFR Section:
50.72(b)(2)(xi) - OFFSITE NOTIFICATION
Person (Organization): RICK DEESE (R4DO)
|
Unit |
SCRAM Code |
RX CRIT |
Initial PWR |
Initial RX Mode |
Current PWR |
Current RX Mode |
|
1 |
N |
N |
0 |
Cold Shutdown |
0 |
Cold Shutdown |
"At approximately 0125 CDT, the AquaDam
providing enhanced flood protection for Fort Calhoun Station Unit 1 failed.
This resulted in approximately 100 gallons of petroleum being released into the
river after a protective barrier was breached and many fuel containers were
washed out to the river. The fuel/oil containers were staged around the
facility to supply fuel for pumps which remove water within the flood
containment barriers. The spill was reported to the State of Nebraska at 10:45
AM CDT on 6/26/2011.
"This condition is being reported
pursuant to 10 CFR 50.72(b)(2)(xi) for News Release or Notification of Other
Government Agency. Applicable governmental agencies have been notified per
plant procedures."
The licensee notified the NRC Resident
Inspector.
|
Power Reactor |
Event Number: 46988 |
|
Facility: FORT CALHOUN |
Region: 4 State: NE |
|
Unit: [1] [ ] [ ] |
RX Type: (1) CE |
|
NRC Notified By: AMY BURKHART |
HQ OPS Officer: HOWIE CROUCH |
|
Notification Date: 06/26/2011 |
Notification Time: 07:58 [ET] |
|
Event Date: 06/26/2011 |
Event Time: [CDT] |
|
Last Update Date: 06/26/2011 |
|
|
Emergency Class: NON EMERGENCY |
|
10 CFR Section:
50.72(b)(3)(iv)(A) - VALID SPECIF SYS
ACTUATION
Person (Organization): R4IRC (WALKER) (R4), RICK DEESE (R4DO)
|
Unit |
SCRAM Code |
RX CRIT |
Initial PWR |
Initial RX Mode |
Current PWR |
Current RX Mode |
|
1 |
N |
N |
0 |
Cold Shutdown |
0 |
Cold Shutdown |
"At approximately 0125 [hrs. CDT], the
AquaDam providing enhanced flood protection for FCS [Ft. Calhoun Station] Unit
1 failed. At 0221, as a precautionary measure, DG-2 [Diesel Generator] was
automatically started per plant procedure to divorce bus 1A4 from offsite
power. At 0250, DG-1 was automatically started to divorce bus 1A3. Both
Emergency Diesel Generators loaded on buses as designed. 345KV and 161KV
offsite power remain available.
"This is reportable pursuant to
10CFR50.72(b)(3)(iv)(A), 'System Actuation of the Emergency Diesel Generators'.
All safety related flood protection barriers remain in place.
"Current river level is 1006.5' MSL and
stable. FCS remains in a NOUE [Notification of Unusual Event] due to high river
level.
"NRC personnel stationed onsite for
flood monitoring have been informed."
June 25th, 2011 at 10:35 AM
- - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - -
8-month-old NRC letter: At 1,010 ft water would
enter Ft. Calhoun’s auxiliary building, shorting power and submerging pumps;
Could then have a station blackout with core damage within 15-18 hours — Water
now at 1,007 ft
[The
water level at Ft. Calhoun nuclear plant] reached a height of nearly 1,007 feet
above sea level at the plant yesterday. [...]
The NRC
responded in its October 2010 letter that once flooding reached 1,004 feet,
water would have entered the plant and the ability of emergency workers to move
around the site would “significantly degrade.” [...]
At 1,010
feet, water would begin to enter the auxiliary building, “shorting power and
submerging pumps. The plant could then experience a station blackout with core
damage estimated within 15 to 18 hours,” under a worst-case scenario, the NRC
said. [...]
“They also ordered us to revise our policies and
procedures and make whatever changes were necessary to bring the design basis
up to 1,014. We did so, and we believe we are now in compliance with the NRC
and are awaiting a final inspection.” -Omaha Public Power District spokesman
Michael Jones

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Other nuclear power plants affected include:
River Bend, Baton Rouge,
Waterford New Orleans
**I’ll
find out which others are in Flood Plain.

Plant is designed to accommodate River Level of 903 Feet Above MSL (Mean Sea Level). This corresponds to 46.5 Ft River Level (as gauged at Brownville, Nebraska)
Current River Level 899.7 Feet Above MSL (43.1 Ft). It was higher yesterday and reached about 901’ Above MSL.

Army Corp of Engineers have started Releasing 160,000 GPM or Water from Upstream Dams. Expected Level at Cooper may exceed 902 Feet.

WHEN Level reaches 902’ Above MSL (45.5 Ft), THEN
Cooper will Shutdown from Power Operation. **
Need to find out if Cooling Plant to Decay Heat Removal is REQUIRED at this
stage or if they will Maintain Hot Shutdown.
Cooper has maximum Decay Heat to remove because both Units are on line. It would take close to 2 Shifts to Lower Temperature enough to go on Residual Heat Removal (if all equipment is functioning).
**I need to
find out when the last Refueling Outages for the Units took place so I can estimate
the Spent Fuel Pool Heat Load.
ο
Swift Flowing Water due to Dam Breaks or Levee
Blowouts (either upstream or down). Intake Structures are not Designed to
handle the unpredictable hydro-dynamics and turbulent flow from rapidly flowing
water.
ο
Power Shortages due to loss of other plants because
of the flooding. This would cause a Demand for Emergency Diesels.
**
Homework Items For Future Reporting
TEPCO hopes to resume water decontamination
http://www3.nhk.or.jp/daily/english/24_04.html
The operator of the crippled Fukushima Daiichi nuclear
power plant hopes to resume the water decontamination process at the plant
within several days.
At the nuclear power plant, a water treatment system started operation last
Friday, but it ceased functioning after only 5 hours due to a sharp rise in
radiation levels in US-made equipment built to absorb radioactive material.
Tokyo Electric Power Company hopes to restart the system and continue the
decontamination process by pouring low levels of contaminated water into the
equipment to decrease radiation levels.
The decontamination process has been halted several times due to a series of
problems.
Although this is the right direction to take in
somewhat controlling the releases from Fukushima, the going is going to be
painfully slow without much reported success. Here’s why:
ο
Dangerous Radiation
ο
High Temperatures
ο
High Humidity
ο
Internal Flooding from Feed and Bleed
ο
Damaged Systems and Structures due to Wreckage
ο
Darkness and Low Visibility
ο
Lack of Skilled Manpower
Look – At the risk of sounding redundant, I
reiterate (again):
IF the goal was to convert a functioning BWR into a
Waste Generation Facility, with NO OFF-SWITCH, I couldn’t have thought of a
better way myself.
http://www3.nhk.or.jp/daily/english/24_33.html
The operator of the Fukushima Daiichi nuclear power plant
says it lost control of an unmanned helicopter during a flight near the No. 2
reactor building, forcing the controller to make an emergency landing on a roof
there.
Tokyo Electric Power Company says the remote-controlled light helicopter took
off from an observatory south of the Fukushima plant just past 6:30 AM on
Friday. Its mission was to collect airborne radioactive substances around the
No. 2 reactor building.
The utility says its engine failed about 30 minutes later, making it impossible
for the aircraft to ascend.
The helicopter -- 50 centimeters long and weighing 8 kilograms -- was found
lying on its side on the rooftop.
TEPCO says it did not see any smoke or flames coming from the helicopter when
it landed, and neither the craft nor the reactor building was damaged.
It says it plans to retrieve the helicopter using a mobile crane.
Fallen device in Monju retrieved – Nothing to do with
Earthquake but shows Lax respect for Nuclear Power
http://www3.nhk.or.jp/daily/english/24_10.html
The operator of Japan's
experimental fast-breeder nuclear reactor Monju has successfully retrieved a
3-ton device that fell inside the reactor vessel 10 months ago.
The Japan Atomic Energy Agency says it completed work to recover the
fuel-exchange equipment at around 5 AM on Friday. The work took about 8 hours.
In May last year, the Monju reactor in Tsuruga, Fukui Prefecture, resumed
operations after a 14-year shutdown. It was closed in 1995 after a sodium leak
started a fire.
But 3 months after restarting, operations had to be suspended again after the
device fell into the reactor during an inspection.
The agency's previous attempts to collect the device failed when it got stuck
against the vessel's upper lid.
The operator will now inspect the reactor for damage before restarting it.
The agency had planned to begin generating electricity early this year. But
substantial delays now appear inevitable.
Monju was supposed to play a central role in Japan's nuclear fuel recycling
program, but its future is now looking increasingly uncertain. The government
says it will review its energy policy in the wake of the nuclear accident in
Fukushima.
Friday, June 24, 2011 10:31 +0900 (JST)